Overview
The Harbor Palms residential neighborhood is comprised of approximately 600 homes. The City acquired the Development’s utilities in the 1980s at the community’s request. Infrastructure improvements are required as the existing utilities are approximately 40 years old, consisting of substandard materials that do not meet City utility design standards. The sidewalks and gutters are deteriorating and the frequent restoration required as a result of utility repairs is further impacting the condition of the roadways and sidewalks. Due to budget constraints, the project will be broken into phases.
Click to view Project Map
Status and History
- Advertisement for Construction February 2019
- Two phases of sewer lining completed
- Phase 1 Construction began July 2019
- Phase 2 Design initiated August 2020
- Phase 1 Construction completed December 2020
- Phase 2 Design initiated January 2021
- Phase 2 Construction advertisement completed February 2021
- Phase 2 Construction began July 2021
Project Scope of Work
- Construct new 2, 4, 6, and 8-inch water mains
- Install new water services and meters
- Construct new 8-inch HDPE water main under Moccasin Creek
- Remove 4-foot wide sidewalks and replace with 5-foot wide sidewalks
- Remove and replace existing curbs
- Rebuild or resurface roadways, including underdrain in areas
- Repair some existing stormwater inlets, replacement of tops and lids
- Restore all work areas to pre-construction or better conditions
Phase 1
Scope of Work
Oakleaf Boulevard | Elmwood Drive |
Lemonwood Drive | Forest Drive |
Greenwood Drive | Hibiscus Circle North, East, and South |
Ironwood Court East and West | Mapleleaf Boulevard |
Schedule
Phase 2
Scope of Work
Oakleaf Boulevard | Azalea Court |
Buttonwood Drive | Maplewood Drive |
Chinaberry Drive | Driftwood Circle North, West, and South |
Phase 2 Map
Projected Schedule
- 75% Design plans completed October 2020
- Public meeting December 2020
- 90% Design plans completed December 2020
- 100% Design plans complete January 2021
- Request Council to advertise January 2021
- Advertise for construction bids February 2021
- Begin Construction June 2021
- Phase 1 (Driftwood, Sothern Oakleaf)
- Phase 2 (Chinaberry, Buttonwood, next section Oakleaf)
- Phase 3 (Maplewood, next section Oakleaf)
- Phase 4 (Azalea, remainder Oakleaf)
- Substantial completion Summer 2022
Phase 3
Scope of Work
Tangerine Drive | Peppertree Drive |
Evergreen Drive | Limetree Drive |
Forest Drive | Greenwood Drive |
Schedule
- Public meeting June 2022
- Construction Plans Completion - July 2022
- Advertise for Construction Bids -August 2022
- Notice to Proceed - Fall 2022
- Construction expected in 2023
- Substantial completion - Fall 2023