Harbor Palms Infrastructure Improvements

Overview

The Harbor Palms residential neighborhood is comprised of approximately 600 homes. The City acquired the Development’s utilities in the 1980s at the community’s request. Infrastructure improvements are required as the existing utilities are approximately 40 years old, consisting of substandard materials that do not meet City utility design standards. The sidewalks and gutters are deteriorating and the frequent restoration required as a result of utility repairs is further impacting the condition of the roadways and sidewalks. Due to budget constraints, the project will be broken into phases. 

Click to view Project Map

Status and History

  • Advertisement for Construction February 2019
  • Two phases of sewer lining completed
  • Phase 1 Construction began July 2019
  • Phase 2 Design initiated August 2020
  • Phase 1 Construction completed December 2020
  • Phase 2 Design initiated January 2021
  • Phase 2 Construction advertisement completed February 2021
  • Phase 2 Construction began July 2021
  • Phase 2 Construction expected completion summer 2023
  • Phase 3 Design initiated January 2022
  • Phase 3 Construction advertised August 2022
  • Phase 3 Construction commencement January 2023
  • Phase 3 expected completion Fall 2023

Project Scope of Work

  • Construct new 2, 4, 6, and 8-inch water mains
  • Install new water services and meters
  • Construct new 8-inch HDPE water main under Moccasin Creek
  • Remove 4-foot wide sidewalks and replace with 5-foot wide sidewalks
  • Remove and replace existing curbs
  • Rebuild or resurface roadways, including underdrain in areas
  • Repair some existing stormwater inlets, replacement of tops and lids
  • Restore all work areas to pre-construction or better conditions

Phase 1

Scope of Work

Oakleaf BoulevardElmwood Drive
Lemonwood DriveForest Drive
Greenwood DriveHibiscus Circle North, East, and South
Ironwood Court East and WestMapleleaf Boulevard

Schedule

  • Complete

Phase 2

Scope of Work

Oakleaf BoulevardAzalea Court
Buttonwood DriveMaplewood Drive
Chinaberry DriveDriftwood Circle North, West, and South

Phase 2 Map

Projected Schedule

  • 75% Design plans completed October 2020
  • Public meeting December 2020
  • 90% Design plans completed December 2020
  • 100% Design plans complete January 2021
  • Request Council to advertise January 2021
  • Advertise for construction bids February 2021

Update January 2023

  • Construction commencement June 2021
  • Driftwood Circle substantially completed April 2022
  • Chinaberry Drive, Buttonwood Drive, Maplewood Drive, Maplewood Circle, Azalea Court (west of Oakleaf) substantial completion expected December 2022
  • Azalea Court east of Oakleaf Boulevard substantial completion expected Winter 2022/2023
  • Oakleaf Boulevard substantial completion expected summer 2023
  • Phase 2 construction expected completion summer 2023
  • Substantial completion Summer 2022

Phase 3

Scope of Work

Tangerine DrivePeppertree Drive
Evergreen DriveLimetree Drive
Forest DriveGreenwood Drive

Schedule

  • Design initiated January 2022
  • Public meeting June 2022
  • Construction documents completed and advertised August 2022
  • Phase 3 Construction commencement January 2023
  • Phase 3 expected completion fall 2023
  1. Timothy Jacobson

    Senior Engineering Technician